Pilot plan

Charge. Check. Ready. - UK ultra-rapid readiness pilot

Prove, on an ultra-rapid charging estate and inside existing charge dwell, that an automated four-channel tyre check converts at commercial rates, finds a material safety and efficiency problem, corrects it without extending the stop, and becomes habitual for repeat chargers.

Pilot plan v1.0, 8 September 2026Operator cost: nilFive hypotheses, three can stop the pilot

The single decision at the end

At week twelve the operator holds a single decision: extend to a paid estate rollout on agreed terms, extend the pilot to a second cohort, or stop with no cost incurred.

Who pays for what

AiR funds, installs, insures and maintains the pilot hardware. The host provides bay footprint, a 230 V supply, permission to operate and site induction. No capital outlay and no service commitment from the operator.

Hypotheses

Five claims that can fail

Each one has a numeric threshold agreed before the first install and a stated failure condition. A pilot that cannot fail proves nothing.

H1

Charging dwell converts to tyre checks at a commercially useful rate.

Pass: At least 12 percent of charge sessions start an AiR session by week eight, on at least three of the pilot sites.

Fail: Below 8 percent with correct signage and app prompting, the dwell conversion thesis is wrong and the channel is deprioritised.

H2

A material share of charging customers are running outside the placard pressure window.

Pass: At least 45 percent of checked vehicles are more than 3 PSI from placard on at least one corner.

Fail: Below 30 percent, the safety and efficiency argument weakens and the proposition becomes convenience-led, not outcome-led.

H3

The check fits inside the charge and never extends the stop.

Pass: 95th percentile AiR session duration under 4 minutes, and median charge-session duration unchanged versus the matched control period.

Fail: Any measurable extension of charge dwell fails the pilot outright, regardless of other results.

H4

The check becomes habitual for regular chargers.

Pass: At least 30 percent of AiR sessions in weeks nine to twelve come from a vehicle seen earlier in the pilot.

Fail: Below 15 percent it is a novelty, not a retention feature, and the commercial model must be re-based on one-off value.

H5

Correction produces a defensible efficiency gain.

Pass: Modelled energy benefit reported as a range, with the lower bound above 0.8 percent for corrected vehicles.

Fail: If corrections are small and rare, the range benefit is not material and the story reverts to safety alone.

Scorecard

Seven metrics, defined and instrumented

Definition, instrument and target for every metric, so the result cannot be re-argued after the fact.

Tyre-check utilisation

Completed AiR sessions divided by charge sessions at the same site over the same period, reported per site and per hour of day.

Instrument

On-unit session counter, reconciled weekly against the operator's own charge-session count for the site.

Target

12 percent by week eight, 18 percent stretch

Whether dwell converts at a rate that supports a national rollout.

Vehicles found under or over pressure

Share of checked vehicles more than 3 PSI from the placard value on at least one corner at entry, split under versus over.

Instrument

Entry pressure on all four channels against the resolved OEM placard value for the vehicle and load condition.

Target

Measure, no target - this is the problem statement

The scale of the safety and efficiency problem inside the operator's own customer base.

Average correction required

Mean absolute PSI delta between entry and exit pressure per corrected corner, and mean corners corrected per vehicle.

Instrument

Per-channel entry and exit readings from the calibrated sensor set, logged per session.

Target

Measure, no target

How far from correct the charging estate actually runs.

Repeat usage

Share of sessions in weeks nine to twelve from a salted registration hash already seen during the pilot.

Instrument

One-way salted hash created on-unit; the plate is never stored and the salt is destroyed at pilot close.

Target

30 percent of late-pilot sessions

Whether the check becomes habitual, which is what makes it a retention feature.

Driver dwell time

AiR session duration, and charge-session duration on the same visit versus the matched control period.

Instrument

Unit session clock, plus operator charge-session duration supplied in aggregate only.

Target

95th percentile under 4 minutes, zero measurable charge extension

That the check sits inside the charge rather than lengthening the stop.

Estimated efficiency improvement

Modelled energy and range benefit from the correction applied, reported as a low-to-high range, never a single point value.

Instrument

Correction magnitude applied to published rolling-resistance sensitivity, with assumptions printed alongside every figure.

Target

Lower bound above 0.8 percent on corrected vehicles

The operator's headline customer-value number.

Customer satisfaction

Two-question on-unit prompt at end of session, scored 1 to 5, plus operator app rating where the operator chooses to share it.

Instrument

On-screen prompt, anonymous, skippable; response rate reported alongside score so a high score on low volume is visible.

Target

4.3 of 5 with a response rate above 25 percent

Whether the service raises perceived value of the hub itself.

Schedule, agreement to decision

  1. Agreement and site selection

    Weeks 1-2

    Two-page pilot agreement, mutual NDA, site shortlist against the published criteria, landlord consents started.

  2. Site survey and design

    Weeks 3-4

    Footprint, hose reach, pedestrian routing, power route and mounting confirmed per site. Method statement and risk assessment issued.

  3. Manufacture and configure

    Weeks 5-8

    Units built and calibrated, host branding applied, offline behaviour and telemetry configured, factory acceptance test witnessed.

  4. Install and commission

    Week 9

    One site per day. Electrical sign-off, calibration verification, eleven-point acceptance script signed per unit.

  5. Soft launch

    Week 10

    Staff walkthrough, signage live, no promotion. Baseline capture and instrumentation reconciliation against operator session counts.

  6. Live pilot, phase one

    Weeks 11-16

    Full operation with signage and in-app prompting. Weekly one-page report every Monday, faults inside 24 hours.

  7. Mid-pilot gate

    Week 17

    Formal review against H1 to H5. Continue, adjust prompting and signage, or stop. Any change is documented and dated.

  8. Live pilot, phase two

    Weeks 18-22

    Repeat-usage window measured, satisfaction sampling completed, efficiency model reconciled against actual corrections.

  9. Results and decision

    Week 23

    Full results pack, assumptions register, control comparison and a rollout proposal with commercial terms. One decision requested.

Site selection criteria

Cohort sizeThree to five hubs, one AiR MAX STATION per hub, plus one matched control hub with no unit
MixAt least one retail-destination hub, one urban hub and one strategic-route hub, so dwell behaviour is not read from a single format
Throughput floorA minimum of 60 charge sessions per site per day averaged over the previous quarter
Physical fitA 2.4 m by 1.2 m footprint reachable by four 8.5 m hoses across at least two bays, without crossing a pedestrian route
PowerOne 230 V 13 A commando or fused supply within 10 m, metered separately where the host requires it
Connectivity4G coverage adequate for telemetry, with the estate mesh as fallback; the unit operates fully offline if both drop
ApprovalsLandlord consent, host safety induction and, where the site sits under a retail lease, written landlord sign-off before install

Responsibilities

AiRHardware, install, calibration, insurance, maintenance, telemetry, reporting, data protection controls and the results pack
Host operatorSite selection input, bay footprint, 230 V supply, permission to operate, safety induction, aggregate charge-session counts
Host site teamReport faults through one named channel, keep the footprint clear, no maintenance duties of any kind
Joint steeringOne 30-minute call per fortnight, one named owner each side, decisions minuted and dated
Independent verificationCalibration certificates and a sample audit of session records by an agreed third party before the results pack is issued

Governance

Cost, data, safety and the stop condition

Hardware, 5 unitsModelled at GBP 33,000 to 42,000 including spares, carried by AiR
Install and commissioningModelled at GBP 2,400 per site including electrical sign-off, carried by AiR
Operate, insure and maintain, 12 weeksModelled at GBP 5,800 across the cohort, carried by AiR
Measurement, audit and reportingModelled at GBP 6,500 including independent sample audit, carried by AiR
Host cash costNil. Footprint, power and permission only
Host staff timeEstimated 6 hours per site across the full programme, mostly at survey and induction

All costs are modelled estimates for discussion, not quoted prices.

Ready to send

The IONITY and Fastned versions

Same plan, same scorecard, different cohort logic and different hook. Copy either message and send it through the published corporate route.

IONITY UK

19 August 2026: First Greenwich Shopping Park hub opens, described as the first of a London pipeline. Twelve bays at up to 400 kW at a high-footfall retail destination, a deliberate step beyond a motorway-oriented network.

Proposed cohort

Greenwich plus two London pipeline sites and one strategic-route hub, with a fourth London site held as the matched control.

Retail-destination dwell is longer and more relaxed than motorway dwell, so Greenwich is the strongest conversion test. Pairing it with one strategic-route hub shows whether the result travels across formats before the pipeline format is frozen.

Why them

  • - The London pipeline format specification is still open, and being written into the hub design now is far cheaper than retrofitting a built estate later.
  • - IONITY sells premium reliability rather than lowest price, and a verified readiness record is a premium-experience asset no competing network holds.
  • - Retail landlords value dwell-time services; a tyre-readiness station strengthens IONITY's case with the host as well as with the driver.
  • - 400 kW charging concentrates high-value drivers with range anxiety, which is precisely the audience for whom a pressure correction is a felt benefit.

The ask: A 45-minute scoping call with hub format and UK network development, then three to five pipeline sites for the twelve-week pilot.

Dear IONITY UK team,

The Greenwich Shopping Park hub, opened on 19 August and described as the first of a London pipeline, is the reason I am writing now rather than later. Hub format is easiest to influence before it is built.

AiR is an intelligent tyre-readiness platform. A four-channel station identifies the vehicle, retrieves the approved pressure profile, checks and corrects all four tyres inside ninety seconds and issues a timestamped readiness record. On an EV that is not a forecourt convenience: rolling resistance is a larger share of energy demand, so a correction is added usable range on the leg the driver has just paid to charge for.

The proposition is one line. Charge. Check. Ready. The battery charges while all four tyres are checked and corrected, inside the existing stop, with no extension to dwell.

I am proposing a twelve-week pilot across three to five sites, with Greenwich as the lead site and one strategic-route hub for comparison. AiR funds, installs, insures and maintains the hardware. IONITY provides footprint, a 230 V supply and permission. There is no capital outlay and no service obligation.

We would measure seven things and publish all of them, including the ones that do not flatter us: check utilisation against charge sessions, share of vehicles outside the placard window, average correction, repeat usage, dwell impact, modelled efficiency benefit and customer satisfaction. Three of the five hypotheses can fail the pilot outright, and the stop condition is written into the plan.

The full pilot plan, scorecard definitions, data-protection controls and safety gates are ready to share, alongside a private dashboard for your team.

Could we find 45 minutes with the colleagues who own hub format specification and UK network development?

Kind regards,
Alexander Macdonald
Founder, AiR - Amporah Ltd
airintelligence.io
Open the IONITY UK dashboard

Fastned UK

20 August 2026: First Liverpool hub opens at Brunswick Business Park, taking the UK estate to forty hubs. Eight 400 kW chargers close to Liverpool city centre and major commercial areas.

Proposed cohort

Brunswick Business Park plus two established hubs at contrasting throughput, and one matched control hub with no unit.

A forty-hub estate is large enough for statistically useful evidence and small enough that one decision moves a meaningful share of the network. Choosing one new hub and two mature hubs separates novelty effect from steady-state behaviour.

Why them

  • - Forty hubs is the sweet spot: a three-site result generalises credibly across the estate rather than being dismissed as anecdote.
  • - Fastned's canopy format and hospitality positioning already treat the hub as a destination, so a readiness service is a format extension, not a new idea.
  • - Commercial and city-adjacent sites like Brunswick attract fleet and high-mileage drivers, where pressure drift is fastest and the benefit is largest.
  • - Fastned publishes performance data openly, which fits a pilot designed to publish its failures alongside its successes.

The ask: A 45-minute scoping call with UK country and partnerships leadership, then two to three hubs on the seven-metric scorecard with an agreed route to estate-wide rollout on the evidence.

Dear Fastned UK team,

Congratulations on the Brunswick Business Park opening on 20 August, and on reaching forty UK ultra-rapid hubs. That estate size is the reason I am approaching you now: it is big enough for a pilot result to mean something and small enough that one decision can move a large share of the network.

AiR is an intelligent tyre-readiness platform. A four-channel station identifies the vehicle, retrieves the approved pressure profile, checks and corrects all four tyres inside ninety seconds and issues a timestamped readiness record. Under-inflation costs an EV more than an equivalent combustion car, because rolling resistance is a larger share of its energy demand. Correcting four tyres during a charge is added usable range on the leg the driver has just paid for.

Charge. Check. Ready. The check happens inside the existing stop and must never extend it - that is written in as a pass or fail condition, not an aspiration.

I am proposing a twelve-week pilot across three hubs: Brunswick as the new-site test, two mature hubs at contrasting throughput, and one matched control hub with no unit. AiR funds, installs, insures and maintains the hardware. Fastned provides footprint, a 230 V supply and permission. No capital outlay, no service obligation, and a stop condition that costs Fastned nothing.

Seven measures, all published: check utilisation against charge sessions, share of vehicles outside the placard window, average correction in PSI, repeat usage, dwell impact against the control period, modelled efficiency benefit reported as a range, and customer satisfaction with its response rate shown alongside.

The full pilot plan, definitions, data-protection controls and safety gates are ready, together with a private dashboard for your team.

Could we find 45 minutes with UK country and partnerships leadership?

Kind regards,
Alexander Macdonald
Founder, AiR - Amporah Ltd
airintelligence.io
Open the Fastned UK dashboard

Pilot results dashboard

Tyres checked, pressure corrected, efficiency saved, repeat usage

The live reporting surface for the twelve-week pilot: six hubs including one matched control, weekly and cumulative, with each hypothesis marked pass or fail against its pre-agreed threshold.

No pilot is live yet. Every figure below is produced by the AiR simulation model so the operator can see exactly what will be reported, in what shape, before committing a single site. Live sessions replace these values one site at a time as units are commissioned.

Tyres checked

0

5,588 sessions across 5 hubs

Corners corrected

0

26.4% of all tyres checked

Energy saved, modelled

0 kWh

116.8 kg CO2e avoided, at 0.207 kg per kWh

Repeat usage, weeks 9-12

0.0%

Salted plate hash, never a stored registration

Per-site scorecard, twelve weeks

Modelled
HubTyres checkedUtilisationOut of specAvg PSI addedRepeatModelled savingCO2e avoided
Greenwich Shopping ParkIONITY - Retail destination6,46813.1%51%534.8%158.4 kWh32.8 kg
Brunswick Business ParkFastned - Urban3,39210.6%51.5%5.132.5%83.9 kWh17.4 kg
London pipeline hub BIONITY - Urban4,46011.1%54.3%4.931.8%116.2 kWh24.1 kg
Strategic route hubIONITY - Strategic route4,9369%53.4%5.131.6%126.5 kWh26.2 kg
Mature hub, mid throughputFastned - Urban3,09610.4%53.1%531.8%78.9 kWh16.3 kg
Matched control hubFastned - Control0------

The control hub carries no unit. It exists so any change in charge-session duration or throughput can be read against a site the pilot never touched. Select any live hub to open its weekly detail.

Weekly detail

Greenwich Shopping Park

Wk 1364
Wk 2332
Wk 3456
Wk 4484
Wk 5484
Wk 6560
Wk 7560
Wk 8640
Wk 9648
Wk 10624
Wk 11700
Wk 12616

Median session

102s

Satisfaction

4.4 / 5

Efficiency band

1.1-2.1%

Energy saved

158.4 kWh

CO2e avoided

32.8 kg

Hypothesis verdicts

H1 Dwell converts to checks

10.8% of charge sessions

H2 Material share outside placard

52.7% of checked vehicles

H3 Check fits inside the charge

103s median session

H4 Check becomes habitual

32.5% repeat in weeks 9-12

H5 Defensible efficiency gain

1.1% to 2.1% modelled

A failed hypothesis is reported to the operator exactly as shown here. The stop condition is part of the agreement, and control-hub data is published alongside every claim.

Control hub: Matched control hub, 7,672 charge sessions observed, no AiR unit installed